How to demolish a house in New Smyrna Beach, FL
In New Smyrna Beach, residential demolition permits are issued by the City of New Smyrna Beach Building and Inspections Division (application: Building permit (Demolition) submitted in EnerGov Citizen Self Service). If the house is a designated landmark or sits in a local historic district, review by the Historic New Smyrna Beach Preservation Commission (HPC); a pending Chapter 50 update would rename it the Historic Preservation Board comes first.

Demolition permit steps in New Smyrna Beach
Step 1
If the house is a contributing building in either National Register district, or a designated landmark or in a local historic district, apply to the historic preservation commission first; the demolition permit is withheld until that process is complete (Sec. 50-12(n)).
Step 2
Register and submit the permit in EnerGov Citizen Self Service, adding the homeowner and any subcontractors.
Step 3
Pay fees and track status in Citizen Self Service.
If the house is historic in New Smyrna Beach
Who reviews it: Historic New Smyrna Beach Preservation Commission (HPC); a pending Chapter 50 update would rename it the Historic Preservation Board.
When it applies
- Demolition of a contributing building in either of the city's two National Register of Historic Places historic districts (Historic Building Demolition Ordinance, Sec. 50-12(e)). The city's districts include the New Smyrna Beach Historic District and the Coronado Historic District.
- Demolition of a designated landmark, landmark site, or property in a designated local historic district requires a certificate of appropriateness (Sec. 50-8(a)).
How the review works
- Newspaper notice by commission staff at least 30 days before the hearing; the owner must send certified mail, return receipt requested, to all property owners within 150 feet at least 15 days before the hearing (Sec. 50-12(f)).
- Commission determines whether the building is historically significant under ten criteria (Sec. 50-12(g)).
- No demolition approval until the applicant shows no other feasible alternative to demolition (Sec. 50-12(g)).
- If significant, approval only on undue economic hardship, unsound building condition, or lack of alternative (Sec. 50-12(h)).
- For certificates of appropriateness the commission holds a hearing within 30 days of a complete application and acts within 60 days after the hearing; a certificate is not effective for 15 days after the decision (Sec. 50-8).
- Appeal to the City Commission within 15 days (Sec. 50-12(m)).
What the board can ask for
- Economic hardship report: price paid, date and seller; two most recent assessments; two years of taxes and debt service; appraisals within two years; listings, asking price and offers; consideration of adaptive uses including possible fair market rents (Sec. 50-12(h)(1)).
- Building condition claim: written report signed by a licensed engineer or architect experienced in historic restoration stating the building is structurally unsound and unsuitable for restoration; commission and staff may inspect inside and out (Sec. 50-12(h)(2)).
- Lack of alternative claim: written documentation of attempts to sell at a reasonable comparable price or to offer the building free to anyone willing to move and preserve it, with appraisals or comparables (Sec. 50-12(h)).
- Certificate of appropriateness application: drawings of proposed work, photographs of the building and adjacent properties, building material information (Sec. 50-8(b)).
- Conditions of approval may include a written and pictorial record of the building's history and architectural features for archival purposes (Sec. 50-12(i)(1)).
Demolition delay: If the building is historically significant and no allowing circumstance is met, the commission sets a demolition delay of up to 120 days from the date of application to investigate alternatives with the owner (Sec. 50-12(j)).
Relocation, salvage and donation: Applicant claiming no alternative must document offering the building without charge to purchasers willing to move and preserve it. Approval conditions may require allowing salvage of the historic building, archaeological study before or during demolition, and replacement design meeting the city's Historic Preservation Design Guidelines (Sec. 50-12(h) and (i)).
Utilities, asbestos, septic and trees in New Smyrna Beach
The office that issues it
State rules apply on top of the local ones
The asbestos notice, septic and well abandonment, owner-builder limits and the Notice of Commencement come from state law. See the Florida rules that apply to every demolition.
Straight answers
Do I need a permit to demolish a house in New Smyrna Beach?
Yes. Residential demolition in New Smyrna Beach is permitted through the City of New Smyrna Beach Building and Inspections Division. Fee: Residential exterior/interior demolition is in Group II of the permit fee schedule (Rev 10-1-2025), priced by valuation: for example $100.85 up to $2,500 and $229.80 for $2,500.01 to $8,500, plus a state surcharge of 2.5% or $4.00, whichever is greater. Fifty percent of the permit fee is paid in advance for plan review and is not refundable..
What if my house is historic in New Smyrna Beach?
If the house is a local landmark or in a local historic district, Historic New Smyrna Beach Preservation Commission (HPC); a pending Chapter 50 update would rename it the Historic Preservation Board reviews the demolition before a permit can issue. If the building is historically significant and no allowing circumstance is met, the commission sets a demolition delay of up to 120 days from the date of application to investigate alternatives with the owner (Sec. 50-12(j)).
Can Brightview handle the demolition in New Smyrna Beach?
Yes. Brightview Homes (CRC1334100) pulls the permit under its Florida contractor license and runs the asbestos survey and notice, utility disconnects, historic documentation when it applies, tear-down, haul-off and final inspection. Demolition is quoted per job, typically $12,000 to $24,000.
Where this comes from
Every fact on this page comes from the official sources below, read on the date shown. Rules change; the building department has the final word.
- NSB Building and Inspections
https://www.cityofnsb.com/69/Building-Inspections - NSB Certificates of Appropriateness
https://www.cityofnsb.com/1413/Certificates-of-Appropriateness - NSB Code Ch. 50, Historic Preservation (Municode)
https://library.municode.com/fl/new_smyrna_beach/codes/code_of_ordinances?nodeId=PTIICOOR_CH50HIPR - NSB Chapter 50 Historic Preservation Update
https://www.cityofnsb.com/1431/Chapter-50-Historic-Preservation-Update - NSB Planning Department Fees
https://www.cityofnsb.com/DocumentCenter/View/16779/Planning-Department-Fees - NSB Permit Fee Schedule (Rev 10-1-2025)
https://cityofnsb.com/DocumentCenter/View/20058/PERMIT-FEES-10-1-25 - https://newsmyrnabeachfl-energovweb.tylerhost.net/apps/SelfService#/home
https://newsmyrnabeachfl-energovweb.tylerhost.net/apps/SelfService#/home - https://volusia.floridahealth.gov/programs-services/environmental-public-health/ostds-septic-and-sewer-systems/
https://volusia.floridahealth.gov/programs-services/environmental-public-health/ostds-septic-and-sewer-systems/
What we could not confirm in published sources
Ask the building department about these before you plan around them.
- Demolition submittal checklist (survey, utility disconnects, asbestos) for NSB; not found on a primary page.
- Whether the Chapter 50 update (renaming the board, clarifying demolition of contributing structures, higher fines) has been adopted; Municode still shows the older text.
- Exhibits A and B district maps referenced in Sec. 50-12 are on file at the city, not online in the code.
- Which local landmarks or local historic districts exist today.
- Utility provider disconnect rules (NSB Utilities Commission) and tree permit rules.
Get this scope quoted in Volusia County
Send the address or parcel ID. A real person replies within one business day with a written proposal. Nothing is ordered and nothing is charged until you approve it.
Prefer Spanish? Our team works with you in English or Spanish, from the county board to the permit counter.
- Residential Demolition